Utility demand charges are a bitch.

50kVA for a fast charger, I have read. That implies 69kVA source for circuit sizing and generate/transform/rectify efficiency (idk, 90%?) 334A at 208V per car, I guess.

More than 5 MW with all spaces full and 3/4 in charging state. They could not afford to fill the lot on utility power. They would also need a capacitor bank to treat 5MW of reactive load.

EE bros check my estimate.

[–] 0 pt

That's a good estimate, and that's two houses worth of full load for one car.